 Week4 - Concrete prep and plumbing rough

We’re ready to pour concrete. Last few items to inspect today before we get concrete delivered.

Vapor barrier is down and lapped over. Want to make sure we don’t have any big gaps in there esp where we finish the floor and will be unable to see it if there is moisture building up. 

Rebars come next, over the vapor barrier. We made the spring closer to make it more rigid. Thankfully we did not have any extra labor cost from that (Amen!)

Plumbers then came back and taped up to the vapor barrier.  Also, we checked that they have insulayfoam around their pipes. This helps a lot once concrete is poured as it gives them wiggle room for final fixture locations 

Me and my family are excited for the concrete pour. We are all set!!!

O U R  P R O C E S S :
website: https://alt-ark.com

#homesteadarchitect #texasarchitect #dfwarchitect #homesteading  #texashomestead #homebuild #homesteadbuild #newhomebuilder #homesteadlife #homesteadsystems #farmhouse #homebuilder #homestyling #buildtheark #permaculturedesign #modernfarmhouse
#tspfriends #grownostr #exodus 
https://m.primal.net/JzPZ.png
https://m.primal.net/JzPa.png
https://m.primal.net/JzPc.png
https://m.primal.net/JzPb.png