Bitcoin Mining Firm Bitdeer Partners With Ohio Port Authority for 570 MW Expansion. Bitdeer Technologies Group has signed a lease agreement with the Monroe County Port Authority to secure an additional 570 megawatts (MW) of power capacity. This expansion brings Bitdeer’s total global capacity to 2.5 gigawatts (GW). Bitdeer Expands Power Capacity With New Partnership in OhioBitdeer, a Nasdaq-listed company, has leased land at the Hannibal Industrial Park in Clarington, Ohio, for 30 years. This site, previously an aluminum processing facility, offers existing power infrastructure and utility switchyards capable of supporting large-scale loads. The first phase of this project, providing 266 MW, is expected to be operational by the third quarter of 2025. The remaining 304 MW is under review for incorporation into the regional transmission planning process.